Namibia
Namibia – hope & gorob
Hope COPPER-GOLD PROJECT
(Updated 10 October 2026 – Refer to our announcements page for subsequent updates)
Hope Copper-Gold Mine, Namibia
Situated within the highly prospective Matchless Copper Belt of Central Namibia the Hope & Gorob Copper‑Gold project entered production in late 2026 following an exceptionally rapid development phase. It represents one of the few, and possibly the only, significant commercial hard‑rock copper mines to be brought into production from exploration by an emerging AIM‑listed company in over 15 years, marking a remarkable achievement as the Company transitions into revenue generation.
Run‑of‑mine ore is processed via on‑site ore sorting, then transported to the Tsoaxaub Metals flotation facility to produce copper‑gold concentrate.

Project Highlights
- Mining Licence ML246 granted for a period of 15 years until 31 March 2040
- 2023 JORC (2012) Mineral Resource Estimate: 15.2Mt at 1.2% Cu, containing approximately 190kt of copper across the Hope, Gorob, Vendome and Anomaly deposits.
- April 2026 Updated Independent Mineral Resource: Over 3.0Mt at 1.2% Cu for the Hope open pit, establishing an estimated initial mine life of 7 years.
- Additional Growth Potential: Significant mineralisation occurs outside the current pit shell and has not yet been included in the 2026 Resource Estimate.
- Additional gold upside and exploration potential across the broader licence package.
- Highly successful ore sorter sighter and optimisation test work resulted in the adoption of ore sorting as the initial pre-concentration method for Run-of-Mine ore.
- Reduced capital costs achieved through the use of dry ore sorting and the acquisition of the Tsoaxaub processing plant resolved issues associated with the lack of water at the Hope & Gorob mine site.
- Mining, haulage and logistics inputs have been refined with contractor support and remain consistent with financial modelling assumptions.
- Test work indicates improved copper recovery, reduced dilution from fines, lower pressure on milling capacity and continued support for rapid capital payback. Current projections indicate capital payback achievable in less than 20-months.
- Robust development case indicating strong returns and meaningful upside from further resource growth and operational optimisation.
2023 JORC (2012) Indicated & Inferred Mineral Resource Estimate for Hope & Gorob

* Gross representing 100% estimated resources – Bezant holds a 90% interest in the Hope & Gorob Project
2026 Mine Development

Hope & Gorob Mine groundbreaking ceremony with the local Topnaar community

New Fleet Arriving at Hope Mine

Hope open pit after the first blast

Waste Stripping Hope Open Pit

Grade control operations team

Entrance to Tsoaxaub Metals – formerly NLZM

Tsoaxaub Flotation Plant

Tsoaxaub Flotation Plant Upgrade

Plant commissioning

New Surge Tank Installation

New Haul Trucks for Transfer to Walvis Bay Terminal

Mine site core yard constructed

Emine Site Accommodation
Future Development Strategy
Current planning indicates an initial minimum seven-year open-pit operation at Hope, followed by underground mining and later production from Gorob and Vendome and other known extensions.
All development infrastructure is in place and operating, including haul roads, the upgraded Tsoaxaub Metals flotation plant, and proven ore sorting systems that are actively processing mine material to produce copper‑gold concentrate.
Phase II expansion planning is underway, focused on a tandem processing plant to increase throughput by up to 40% using ore from the existing Hope & Gorob resource. Further step‑out and expansion drilling will follow once stable production and cash flow are established, an initial 500,000 tonnes of contained copper is targeted which is the anticipated minimum criteria for a possible standalone plant under Phase III development.
Gold is currently under‑represented outside Hope in the formal resource model due to historic assay limitations, though drilling and sampling indicate wider copper‑gold potential across the project area. Gold credits offer valuable by‑product upside, and further drilling and geological review are expected to identify higher‑grade zones and support future resource upgrades.
Background Geology & Mine Development
The Matchless Copper Belt is a well-known volcanogenic massive sulphide (VMS) district located within the Damara Orogenic Belt. The belt is characterised by deformed and metamorphosed mafic volcanic and intrusive rocks, including amphibolite, gabbro, amphibolite schist, and chlorite schist.
Mineralisation along the belt is interpreted as Besshi-type volcano-exhalative sulphide deposits, formed by exhalation on the ancient seafloor as stratiform lenses and sheet-like accumulations.
At the Hope & Gorob Copper-Gold Mine, mineralisation is hosted in schist units and concentrated within pyrite‑magnetite‑quartzite bearing lenses.
